IL Rte. 59 & Grand Ave. Improvements
More Images
Complete reconstruction of IDOT & County roads with new underground utility infrastructure.
Owner:
Lake County Division of Transportation
Location:
Fox Lake, IL
Moved on site:
28,770 CY
Trucked off:
19,400 CY
Water Main Installed:
2,069 LF
Storm Sewer Installed:
8,351 LF
Total:
48,170 CY / 10,420 LF
Westview Crossing
More Images + Video
Mass Excavation to develop 150 housing lots, complete with storm water drainage basins.
Owner:
Lennar Corporation
General Contractor:
Lennar Corporation
Location:
Algonquin, IL
Moved on site:
220,000 CY
Trucked in:
15,000 CY
Total:
235,000 CY
Prime Data Center
More Images + Video
72 MW Data Center, Building was 380,141 square feet.
Owner:
Prime Data Centers, LLC
General Contractor:
Clune Construction
Location:
Elk Grove Village, IL
Moved on site:
86,700 CY
Detailed excavation:
10,500 CY
Total:
97,200 CY
Johnsburg High School Athletic Complex
More Images
New sports facility with football, baseball & softball turf fields. Included a new parking lot, tennis courts & track.
Owner:
Johnsburg School District 12
General Contractor:
Byrne & Jones Construction
Location:
Johnsburg, IL
Moved on site:
36,160 CY
Granular for turf field:
8,100 CY
Total:
44,260 CY
NTT Data Center
More Images + Video
Total of 90 MW multiple Data Center Buildings with a ComEd Substation.
Owner:
NTT Global Data Centers CH, LLC
General Contractor:
Clune Construction
Location:
Itasca, IL
Moved on site:
406,120 CY
Detailed excavation:
49,400 CY
Total:
455,520 CY
Cyrus Almond
More Images + Video
54 MW Data Center with Comed Substation.
Owner:
CyrusOne Holdco, LLC
General Contractor:
Clune Construction, IL
Location:
Aurora, IL
Moved on site:
252,300 CY
Detailed Excavation:
23,600 CY
Exported Material:
27,300 CY
Total:
303,200 CY